Skip to content

Getting the campus network ready for the AI era

The Office of Information Systems and Technology is upgrading the wired and wireless network across the Gwanak and Yeongeon campuses over three years. It aims to support teaching and research with a faster, more secure network and wider coverage.

What will change

  • Classroom Wi-FiAny seat, strong Wi-⁠Fi

    Easy wireless access anywhere in classrooms and labs

  • Better campus networkBig files, sent in a flash

    Faster, more reliable wired internet

  • Stronger securitySolid security, your data safe

    Stronger protection, less worry about hacking and data leaks

  • Large eventsPacked rooms, Wi-⁠Fi in every corner!

    Smooth Wi-⁠Fi for everyone at seminars and events

  • Easy wireless access anywhere in classrooms and labs

  • Faster, more reliable wired internet

  • Stronger protection, less worry about hacking and data leaks

  • Smooth Wi-⁠Fi for everyone at seminars and events

Main GateGymnasiumUndergraduate HousingEngineeringHumanitiesSocial SciencesBusiness AdministrationAgriculture & Life SciencesFine ArtsEducationHuman EcologyVeterinary MedicinePharmacyTransdisciplinary InnovationsSchool of Law

© OpenStreetMap · SRTM data courtesy of the U.S. Geological Survey

The entire campus network, renewed over three years

Up nextNetwork equipment installation, Bldgs. 102 and 37 D-36
  1. Done

  2. TodayActive

  3. Later

  4. Later

  5. Later

We will keep this page updated as the schedule progresses.

Year 1: 11 bldgs

  • Switchover
    Sun, Jan 10 (planned)
    Site survey done
    Mon, Sep 14 – Fri, Sep 18These dates are for the on-site survey, not the network switchover.
  • Switchover
    Thu, Jan 7 (planned)
    Site survey done
    Mon, Sep 14 – Fri, Sep 18These dates are for the on-site survey, not the network switchover.
  • Switchover
    Sun, Jan 17 (planned)
    Site survey done
    Mon, Sep 14 – Fri, Sep 18These dates are for the on-site survey, not the network switchover.
  • Switchover
    Thu, Jan 14 (planned)
    Site survey done
    Mon, Sep 14 – Fri, Sep 18These dates are for the on-site survey, not the network switchover.
  • Switchover
    Fri, Jan 1 (planned)
    Site survey done
    Mon, Sep 7 – Fri, Sep 11These dates are for the on-site survey, not the network switchover.
  • Switchover
    Sun, Jan 24 (planned)
    Site survey done
    Thu, Oct 1 – Thu, Oct 8These dates are for the on-site survey, not the network switchover.
  • Switchover
    Sun, Jan 24 (planned)
    Site survey done
    Thu, Oct 1 – Thu, Oct 8These dates are for the on-site survey, not the network switchover.
  • Switchover
    Sat, Jan 30 (planned)
    Site survey done
    Mon, Sep 21 – Wed, Sep 30These dates are for the on-site survey, not the network switchover.
  • Switchover
    Sun, Jan 31 (planned)
    Site survey done
    Thu, Oct 1 – Thu, Oct 8These dates are for the on-site survey, not the network switchover.
  • Switchover
    Wed, Jan 20 (planned)
    Site survey done
    Mon, Sep 21 – Wed, Sep 30These dates are for the on-site survey, not the network switchover.
  • Switchover
    Sun, Dec 27 (planned)
    Network equipment installation
    Fri, Dec 18 – Sat, Dec 19 (planned)no service interruption
    Site survey done
    Mon, Sep 7 – Fri, Sep 11These dates are for the on-site survey, not the network switchover.

Year 1: 11 bldgs

  • Switchover
    Sun, Jan 10 (planned)
    Site survey done
    Mon, Sep 14 – Fri, Sep 18These dates are for the on-site survey, not the network switchover.
  • Switchover
    Thu, Jan 7 (planned)
    Site survey done
    Mon, Sep 14 – Fri, Sep 18These dates are for the on-site survey, not the network switchover.
  • Switchover
    Sun, Jan 17 (planned)
    Site survey done
    Mon, Sep 14 – Fri, Sep 18These dates are for the on-site survey, not the network switchover.
  • Switchover
    Thu, Jan 14 (planned)
    Site survey done
    Mon, Sep 14 – Fri, Sep 18These dates are for the on-site survey, not the network switchover.
  • Switchover
    Fri, Jan 1 (planned)
    Site survey done
    Mon, Sep 7 – Fri, Sep 11These dates are for the on-site survey, not the network switchover.
  • Switchover
    Sun, Jan 24 (planned)
    Site survey done
    Thu, Oct 1 – Thu, Oct 8These dates are for the on-site survey, not the network switchover.
  • Switchover
    Sun, Jan 24 (planned)
    Site survey done
    Thu, Oct 1 – Thu, Oct 8These dates are for the on-site survey, not the network switchover.
  • Switchover
    Sat, Jan 30 (planned)
    Site survey done
    Mon, Sep 21 – Wed, Sep 30These dates are for the on-site survey, not the network switchover.
  • Switchover
    Sun, Jan 31 (planned)
    Site survey done
    Thu, Oct 1 – Thu, Oct 8These dates are for the on-site survey, not the network switchover.
  • Switchover
    Wed, Jan 20 (planned)
    Site survey done
    Mon, Sep 21 – Wed, Sep 30These dates are for the on-site survey, not the network switchover.
  • Switchover
    Sun, Dec 27 (planned)
    Network equipment installation
    Fri, Dec 18 – Sat, Dec 19 (planned)no service interruption
    Site survey done
    Mon, Sep 7 – Fri, Sep 11These dates are for the on-site survey, not the network switchover.

Frequently asked questions

  • Aging network equipment and communications infrastructure will be replaced to make the internet faster and more reliable, and Wi-Fi in classrooms and study spaces will be greatly improved. The campus network will also move to a new IP addressing scheme, strengthen user authentication and access control, and be upgraded to support research that needs high-capacity networking.

  • Year 1 covers 11 buildings and runs through February 2027. The switchover dates shown for each building on this site are planned dates; the actual dates will be confirmed with each building’s contact person.

  • Wired and wireless network service may be briefly interrupted while equipment is installed and switched over. If service is expected to be affected, we will announce the date, time and affected area in advance.

  • Most PC and Wi-Fi users will not need to do anything. Servers, NAS devices, network printers, research and lab equipment, and devices with a static IP address may need to be checked or reconfigured; we will send detailed guidance ahead of each switchover.

  • For questions about the network transition or a building’s switchover schedule, please use the contact details on this website or email snupjt_newnet@snu.ac.kr.

  • This website will keep you informed about transition progress, building switchover schedules, key announcements and how to use the network. We will also share what to prepare and what changes at each stage of the transition.